Recovered $10,525.00 in owner – contractor dispute

The Story:The Plaintiff hired the Defendant to lay interlocking stones to the front patio and back patio. The Defendant failed to complete the work. The Plaintiff attempted to contact the Defendant over the period of a year. However, all of the phone calls went unanswered.

Action:The Plaintiff retained Mississauga Paralegal Services to represent their matter in Small Claim Court. Mississauga Paralegal Services drafted and filed a Plaintiffs Claim against the Defendant for incomplete interlocking work and misrepresentation of services.

Plaintiff claimed:Compensatory Damages.
The Plaintiff wanted the Defendant to either give back their money or complete the job. The Defendant filed a Defence and the matter moved to a Settlement Conference.

Settlement Conference: Photos of the unfinished work were shown and an Offer to settle was presented. Mississauga Paralegal Services drafted the terms of settlement which were then signed by both parties.

Terms of Settlement:

Defendant Shall:
Pay costs of amount claimed.

Repair the following:
Fix loose interlocking stones, close gaps between interlocking stones and level any uneven stones on front and back patio and front and back patio stairs.
Level interlocking stones on front steps.
Minimize cut interlocking stones as several interlocking stones have been cut to fit, cut unevenly and are not consistent in measurements or design.
Complete the grey patterned boarder on front patio.
Correct measurements for back patio to reflect those measurements agreed upon in original contract.
Replace sod to any damaged areas.
Place interlocking under air conditioner to prevent water build up.
Treat weeds growing between interlocking stones.
Apply polymeric sand to interlocking stones and close gaps between stones.
If repairs are not completed, then an additional amount shall be paid to the Plaintiff as the cost to hire another contractor to complete the work.
Ensure that water goes away from the house to the pavement.
Place divider line between interlocking stone and grass.
The repairs shall have a 2 year warranty.
Payment of amount claimed shall be made before November 30th, 2011, prior to the Defendant commencing any repair work.
Repair work shall be completed before April 30 2013.

Outcome of Settlement:Plaintiff awarded:All repair work completed to full satisfaction and payment of $10,525.00
CLIENT SATISFACTION!

The Plaintiff had a strong case with documented photographic evidence of the unfinished work. This type of evidence proves effective when presenting an offer to settle as it significantly weakens a defense before the Courts. There was no question that the Defendant had failed to fulfill their end of the contract and therefore, it was simply a matter or how the Defendant would like to proceed.

When the matter was brought to a settlement conference, the Defendant was faced with a decision of finishing the work to the Plaintiff’s satisfaction and paying costs in consideration of the loss of use of the premise.

To the Plaintiff’s satisfaction, the Defendant decided to pay costs and complete the work!